Checked fact 534519 Nov 2026Money and compute
Nvidia says that in August 2026 it entered into guarantees to provide credit support on the land, power and shell buildout at SB Energy's PORTS-Pike Technology Campus in Ohio, which will exclusively host NVIDIA infrastructure under 20-year leases to OpenAI, subject to limited exceptions.
The exact words it rests on
In August 2026, we entered into guarantees to provide credit support on the land, power, and shell buildout to secure approximately 4.25 gigawatts (GW) across nine buildings at SB Energy's PORTS-Pike Technology Campus in Ohio, which will exclusively host NVIDIA infrastructure under 20-year leases to OpenAI, subject to limited exceptions.
What the source said when we opened it, on 18 Nov 2026.
The source
CFO Commentary on Third Quarter Fiscal 2027 Results (Exhibit 99.2 to Form 8-K)
Checked
Checked by the notis newsroom on , against the source above.
In the story
Nvidia guarantees up to $105 billion for the Ohio site hosting OpenAI-leased systems 19 Nov 2026